Worked Example: Barton Peveril Live Pastoral Analytics

This walkthrough traces a complete Wire engagement from initial kick-off through delivery handover, using a real-world further education client. It covers every command in the canonical sequence and shows two Wire Agents features in practice: auto-delegation during the design phase, and batch dispatch via /wire:delegate at the start of development.

The engagement is a full_platform release using BigQuery, dbt, Looker, and dbt Cloud for orchestration.

Engagement overview

ClientBarton Peveril Sixth Form College, Hampshire
EngagementLive Pastoral Analytics (SOW 2)
Duration2 weeks (Feb 2–13, 2026)
Release typefull_platform
Orchestrationdbt Cloud (scheduled jobs + CI/PR job)

SOW deliverables: Live pastoral pipeline (ProSolution + Focus → BigQuery), Looker semantic layer, SPA Operational Dashboard, data team and end-user training, technical documentation.

Phase 1: Requirements (Day 1)

Engagement setup

/wire:new
→ Client: Barton Peveril Sixth Form College
→ Engagement name: barton_peveril
→ Release type: full_platform
→ Release ID: 01-barton-peveril-live-pastoral
→ Branch: feature/barton-peveril-live-pastoral
→ .wire/releases/01-barton-peveril-live-pastoral/status.md created
16 artifacts across 6 phases, all at not_started

After /wire:new, copy the SOW PDF and ProSolution SQL schema examples into releases/01-barton-peveril-live-pastoral/requirements/.

Requirements — auto-delegated to discovery-analyst

/wire:requirements-generate 01-barton-peveril-live-pastoral
→ [auto-delegated to discovery-analyst agent]

The agent reads the SOW and SQL examples and produces a 13-section requirements specification: FR-1 through FR-9 with acceptance criteria, NFR-1 through NFR-7 (performance, security, freshness SLAs), and a deliverable-to-artifact mapping. It appends two entries to decisions.md:

  • Modelled attendance at daily-snapshot grain, not register-level — register-level would require 6× the Fivetran MAR volume
  • Excluded student_notes.body from replication scope — free-text pastoral records create a GDPR data minimisation risk
/wire:requirements-validate 01-barton-peveril-live-pastoral
→ [auto-delegated to discovery-analyst agent]
→ PASS

/wire:requirements-review 01-barton-peveril-live-pastoral
→ [main session — review gates stay with the consultant]
→ Fathom context: pre-engagement call transcript pulled
→ Approved by Head of MIS, 2026-02-03

Delivery playbook

Before moving into design, generate a playbook for the full release:

/wire:playbook-generate 01-barton-peveril-live-pastoral

The command reads the approved requirements, SOW timeline, and status.md and produces a Mermaid control-flow diagram plus a narrative step guide at planning/live_pastoral_analytics_playbook.md. The ✅ and 🔄 markers on phase headings update each time you regenerate — the version below was produced mid-engagement after design was complete.

The narrative guide covers prerequisites, open questions, and offline activities for each step. Two open questions surface at generation time: PD-2 (confirm the role of note_type_id = 31 in Focus before the dbt review is approved) and PD-11 (FSA Stage 2/3 snapshot data — may need to defer to Phase 2 scope).

What Wire does and does not do. Wire writes the artifacts: requirements, pipeline design, data model, dbt SQL models, LookML, UAT scripts, deployment runbooks, training plans, and documentation. It also runs all mechanical validations. Wire does not take decisions on the team's behalf — every -generate is followed by a -validate and a -review, and the review is the human gate where a named stakeholder approves the artifact before the next phase begins.

Each session should start with /wire:status to confirm the current artifact state, then scope to advancing one artifact through one gate. For development artifacts, generate + validate typically fit in one session. When a review returns changes_requested, re-generate and re-validate before going back to the reviewer. Log open questions immediately with a named owner.

This is a planning utility — it creates no tracked artifact and blocks nothing. Regenerate after any significant scope change to refresh the ✅ markers.

Phase 2: Design (Days 2–4)

Conceptual model — auto-delegated to data-designer

/wire:conceptual_model-generate 01-barton-peveril-live-pastoral
→ [auto-delegated to data-designer agent]

Produces a business-level entity model: five domain entities (Student, Attendance, PastoralNote, SPAAlert, Assignment) with a Mermaid erDiagram showing cardinalities.

/wire:conceptual_model-validate 01-barton-peveril-live-pastoral
→ [auto-delegated to data-designer agent] → PASS

/wire:conceptual_model-review 01-barton-peveril-live-pastoral
→ [main session]
→ Approved by Head of MIS + Head of Student Services, 2026-02-04
→ Decision: SPAAlert is a first-class entity, not a flag on PastoralNote

Pipeline design — auto-delegated to pipeline-engineer

/wire:pipeline_design-generate 01-barton-peveril-live-pastoral
→ [auto-delegated to pipeline-engineer agent]

Produces the full pipeline architecture document: ProSolution source schema analysis, three Fivetran connectors (ProSolution SQL Server CDC, Focus CDC, MIS Applications for risk weights), and 12 design decisions. The design went through five versions before approval. Key decisions: attendance percentage calculated dynamically in Looker (CR-1, never stored); risk scoring from live Looker_Risk_Score table via Fivetran rather than a static seed (CR-3); focus.users removed from CDC scope (CR-5). Open question PD-2 carried forward: confirm the role of note_type_id = 31 before the dbt review is approved.

/wire:pipeline_design-validate 01-barton-peveril-live-pastoral → PASS
/wire:pipeline_design-review 01-barton-peveril-live-pastoral
→ Approved v5.0, 2026-02-25 — five rounds incorporating CR-1 through CR-6

Data model — auto-delegated to data-designer

/wire:data_model-generate 01-barton-peveril-live-pastoral
→ [auto-delegated to data-designer agent]

Produces _sources.yml for all three Fivetran connectors, a physical ERD, and a full model inventory across six versions:

  • 9 staging models, 1 integration model (int__student_xref — cross-system student identity resolution), 7 warehouse models: attendance_fct, pastoral_notes_fct, spa_alerts_fct, assignment_marks_fct, student_risk_score_fct, student_risk_summary, student_risk_history
  • 3 seeds: grade_ordering.csv, focus_note_type_mapping.csv, tracked_assignment_titles.csv
  • All facts use incremental (merge) materialisation
/wire:data_model-validate 01-barton-peveril-live-pastoral → PASS
/wire:data_model-review 01-barton-peveril-live-pastoral
→ Approved v6.0, 2026-02-25 — six rounds
→ student_risk_history added in v5 to accumulate snapshots over time

Mockups

/wire:mockups-generate 01-barton-peveril-live-pastoral
→ [main session — no specialist agent for wireframes]
Dashboard Mockups Generated

File: design/mockups/spa-operational-dashboard.html — open in any browser

What's in it:

- Daily Caseload — 4 KPI tiles (Active Risk 12, Monitoring 8, Unanswered
Alerts 3, No Concerns 45), 6-week at-risk trend line, caseload doughnut,
8-row student priority table with risk signals. Click any row to drill
to Student Detail.
- Student Detail — example student; KPIs for attendance (76%), open alerts,
notes, CAP below target; stacked attendance bar (8 weeks), horizontal bar
grades vs MEG, pastoral notes table, SPA alerts table with wellbeing flag
footer.
- Note Volume Monitor — college-wide note volumes by department, stacked
horizontal bar (4 note types × 7 departments), breakdown table with WoW
% change.
- High-Risk Cohort — dual-risk cohort (wellbeing + att<90%), unanswered
alerts, risk score ranking bar chart, alert age chart, two tables for the
two cohort cuts.

All charts are Chart.js 4.4.1, fully interactive. Sidebar collapses, tabs
switch without page load, filter pills are styled correctly.

A self-contained interactive HTML prototype — no build step, no server. SPAs and pastoral leads review it in a browser before any Looker work begins.

SPA Operational Dashboard mock — Daily Caseload tab

/wire:mockups-review 01-barton-peveril-live-pastoral
→ Approved 2026-02-06
→ Change request: add "days since last SPA contact" column

End of Week 1 — close the session

All four design artifacts approved. Before switching off:

/wire:session:end 01-barton-peveril-live-pastoral

Wire summarises: 6 artifacts completed, two open items (OQ-2 still open), next session focus is Phase 3 Development, recommends starting with /wire:delegate.

Phase 3: Development (Days 5–8)

Day 5 morning — resume and plan

New session, two days later:

/wire:start
→ Select: 01-barton-peveril-live-pastoral
→ Choose: Plan session

Wire shows the release state (6/16 artifacts done), lists the next four at not_started, surfaces the two open items, and recommends /wire:delegate.

Batch dispatch with /wire:delegate

/wire:delegate 01-barton-peveril-live-pastoral

Wire inspects status.md, identifies all development artifacts at not_started, and presents the delegation plan. With 9 staging models and 7 warehouse models in scope, the dbt step fans out across parallel agents per layer:

Delegation plan — Barton Peveril Live Pastoral Analytics / 01-barton-peveril-live-pastoral
───────────────────────────────────────────────────────────────────────────────────────────

Step 1 (sequential):
pipeline-engineer → pipeline-generate
(ProSolution SQL Server CDC + Focus REST API connectors)

Step 2 (multi-wave fan-out, starts after Step 1):

Wave 2a — Staging layer (2 parallel agents):
dbt-developer [staging 1/2] → stg_prosolution__students, stg_prosolution__courses,
stg_prosolution__enrolments, stg_prosolution__attendance,
stg_prosolution__targets (+3 seeds)
dbt-developer [staging 2/2] → stg_focus__attendance_observations,
stg_mis__timetable_slots,
stg_mis__staff_absence,
stg_mis__exam_results

Wave 2b — Integration layer (1 agent, starts after Wave 2a):
dbt-developer [integration 1/1] → int__student_unified_profile

Wave 2c — Warehouse layer (2 parallel agents, starts after Wave 2b):
dbt-developer [warehouse 1/2] → student_dim, course_dim,
attendance_summary_fct, exam_performance_fct
dbt-developer [warehouse 2/2] → student_risk_scores_fct, student_risk_summary,
student_risk_history

Total dbt-developer agents: 5 (2 + 1 + 2)

Step 3 (parallel, starts after Step 2):
3a orchestration-engineer → orchestration-generate (dbt Cloud job config)
3b semantic-layer-developer → semantic_layer-generate (LookML views + explores)

Total: 8 specialist agents across 4 execution stages. Review commands stay in this session.

What the agents produce

pipeline-engineer — Fivetran connector config for ProSolution (SQL Server CDC) and Focus (REST API), plus a Cloud Function for Focus auth token refresh. Error handling: dead-letter queue to pipeline_errors BigQuery table, Slack alerting on consecutive failures.

dbt-developer — 5 agents ran across 3 sequential waves. Wave 2a (2 staging agents in parallel) ran concurrently with each other. Wave 2b ran the single integration model. Wave 2c ran 2 warehouse agents in parallel. Total: 19 SQL models (9 staging, 1 integration, 7 warehouse, 2 utility) plus 3 seeds and 34 static-analysis tests. Surrogate keys via dbt_utils.generate_surrogate_key(); all facts incremental with merge strategy. Static analysis PASS with two findings the team must fix before requesting review: ref() calls inside transformation CTEs in two models (must move to source CTEs at the top of the file); missing s_ prefixes on source CTEs across several warehouse models. Both corrected before the review is requested. Adds to decisions.md:

  • student_risk_summary materialised as table with full_refresh=false — model accumulates historical snapshots; incremental would require a unique_key that changes the grain

orchestration-engineer — Generates the dbt Cloud job configuration (dbt_cloud_config.md):

## Jobs

### barton_peveril_scheduled_run
- Environment: Production (bp-analytics, target: prod)
- Schedule: every 30 minutes (matches NFR-3 freshness SLA)
- Commands:
dbt run --select staging+ warehouse+
dbt test --select staging+ warehouse+
- On failure: Slack → #pastoral-data-alerts

### barton_peveril_ci
- Trigger: pull request against main
- Commands: dbt build --select state:modified+
- On completion: GitHub PR status check

Adds to decisions.md: scheduled job runs on cadence regardless of source readiness — downstream freshness tests surface stale data via Slack alert, which is simpler than sensor-based gating at this data volume. CI job uses state:modified+ to keep PR feedback fast; production job uses full selector to prevent silent exclusions after a merge.

semantic-layer-developer — LookML views for all 7 warehouse models and 5 explores: student_risk_summary, pastoral_notes, attendance, assignment_marks, student_risk_score. attendance_percentage calculated dynamically as SUM(sessions_present) / (SUM(sessions_present) + SUM(sessions_absent)) — never stored (CR-1). Risk signal measures: attendance_deterioration_flag, pastoral_note_spike_flag, unanswered_alert_flag, days_since_last_spa_contact.

Development reviews (Days 6–8)

Review gates stay in the main session:

/wire:pipeline-review 01-barton-peveril-live-pastoral → Approved 2026-02-11
/wire:dbt-review 01-barton-peveril-live-pastoral → Approved 2026-02-11
/wire:orchestration-review 01-barton-peveril-live-pastoral
→ data engineering lead (dbt Cloud admin)
→ Job selectors verified, 30-minute schedule confirmed against NFR-3
→ Approved 2026-02-11
/wire:semantic_layer-review 01-barton-peveril-live-pastoral → Approved 2026-02-12

With semantic_layer approved, generate the dashboard:

/wire:dashboards-generate 01-barton-peveril-live-pastoral
/wire:dashboards-validate 01-barton-peveril-live-pastoral → PASS
/wire:dashboards-review 01-barton-peveril-live-pastoral → Approved 2026-02-12

Phase 4: Testing (Days 9–10)

/wire:data_quality-generate 01-barton-peveril-live-pastoral
→ [auto-delegated to data-quality-engineer agent]

Adds: 30-minute freshness Slack alert, row count reconciliation (ProSolution vs attendance_fct, ±2% tolerance), null rate monitoring, FK hit rate check.

/wire:data_quality-validate 01-barton-peveril-live-pastoral → PASS
/wire:data_quality-review 01-barton-peveril-live-pastoral → Approved 2026-02-13

UAT with SPAs and pastoral leads:

/wire:uat-generate 01-barton-peveril-live-pastoral

UAT plan mapped to FR-1 through FR-9. One iteration: "days since last SPA contact" needed rounding to whole days.

/wire:uat-review 01-barton-peveril-live-pastoral
→ Approved by Head of Student Services, 2026-02-13

Phase 5: Deployment (Day 11)

/wire:deployment-generate 01-barton-peveril-live-pastoral

Generates: step-by-step deployment runbook (Fivetran → BigQuery datasets → dbt Cloud environment + jobs → Looker publish), monitoring setup, rollback procedures.

/wire:deployment-validate 01-barton-peveril-live-pastoral → PASS

/wire:utils-deploy-to-dev 01-barton-peveril-live-pastoral
→ All models built, all tests passing in dbt Cloud dev environment,
dashboards visible in Looker dev

/wire:deployment-review 01-barton-peveril-live-pastoral
→ data engineering lead + analytics engineering lead
→ Dev results presented, runbook walked through
→ Approved 2026-02-13

/wire:utils-deploy-to-prod 01-barton-peveril-live-pastoral
→ Fivetran connectors activated
→ dbt Cloud production environment configured and tested
→ Scheduled job (30-minute cadence) and CI/PR job activated
→ Dashboards published to Looker production
→ Monitoring alerts live

Phase 6: Enablement (Days 12–13)

/wire:training-generate 01-barton-peveril-live-pastoral

Data Team Enablement (Day 12 morning): pipeline architecture, dbt model structure, dbt Cloud job operation, LookML extension, hands-on trace of a data point from ProSolution to Looker.

End User Training (Day 12 afternoon): dashboard navigation, interpreting risk signals, data freshness expectations, how to raise a data quality issue.

/wire:training-validate 01-barton-peveril-live-pastoral → PASS
/wire:training-review 01-barton-peveril-live-pastoral → Approved 2026-02-14
/wire:documentation-generate 01-barton-peveril-live-pastoral
→ [delivery-lead agent reads all approved artifacts and decisions.md]

Produces: architecture overview, dbt model reference, dbt Cloud job reference (selectors, cadence, how to change), LookML field catalogue, operational runbook.

/wire:documentation-validate 01-barton-peveril-live-pastoral → PASS
/wire:documentation-review 01-barton-peveril-live-pastoral → Approved 2026-02-14

Archive

/wire:archive 01-barton-peveril-live-pastoral
→ 16 artifacts, 48 generate/validate/review actions, 11 decisions.md entries
→ Jira Epic BP-1 closed

What the engagement produced

ArtifactFormat
Requirements specification.wire/releases/.../requirements.md
Delivery playbook.wire/releases/.../planning/barton_peveril_playbook.md
Conceptual entity model.wire/releases/.../conceptual_model.md
Pipeline design.wire/releases/.../pipeline_design.md
Physical data model.wire/releases/.../data_model.md
Dashboard wireframes.wire/releases/.../mockups.md
dbt project19 SQL models, 3 seeds, 34 tests
dbt Cloud configdbt_cloud_config.md — scheduled run + CI/PR job
LookML5 explores, SPA Operational Dashboard
Technical documentationArchitecture, dbt Cloud job reference, field catalogue, ops runbook
Training materialsData team session + end-user session
decisions.md11 agent decisions recorded across the engagement